Tuesday, June 16, 2026
spot_imgspot_img

Top 5 This Week

spot_img

Related Posts

Bearspaw South Feeder Main replacement project on schedule, City of Calgary says

The City of Calgary has provided an update on the Bearspaw South Feeder Main replacement project.

Bearspaw South Feeder Main replacement project on schedule, City of Calgary says插图

The city claims it is “on schedule” and has achieved a number of significant milestones.


Click to play video: 'Phase 2 of Calgary’s Bearspaw feeder main construction underway'


Phase 2 of Calgary’s Bearspaw feeder main construction underway


Work to replace the existing feeder main, which Mayor Jeromy Farkas has called “terminally ill,” began in late January and is scheduled to be completed by the end of 2026 — a project the city claims will normally take four years.

Story continues below advertisement

However, construction was fast-tracked following two catastrophic breaks in the existing feeder main.


Replacement of the South Bearspaw Feeder Main became a priority after two catastrophic failures of the existing pipe, including this one in Dec. 2025.

THE CANADIAN PRESS/Handout – Ian Royer

The total cost of reinforcing the existing feeder main, including installing a new liner or “slip line” and with it a new steel pipe, parallel to the existing concrete pipe, is budgeted to cost $439 million.

Get breaking Canada news delivered to your inbox as it happens so you won't miss a trending story.

Get breaking National news

Get breaking Canada news delivered to your inbox as it happens so you won’t miss a trending story.

Construction is being done in stages and the city says stage A — which involves “microtunnelling” under 16 Avenue N.W at 44 Street and Home Road as well as on 29 Avenue N.W. near Sarcee Trail — is 51 per cent complete.

It’s a two-stage process,” said the city’s general manager of infrastructure services, Michael Thompson, during a media tour of the project site Monday afternoon near Shouldice Park.

“First we tunnel a concrete pipe. You can see examples of the concrete pipe behind me. Once that’s all installed, we (will) push a steel pipe inside that concrete pipe. We’ve broken that microtunnelling into five different segments. Two of those segments are already complete.”

Story continues below advertisement

The shafts being dug during in the microtunnelling are about 15 to 20 metres deep.

A map, showing where the new "concrete carrier pipe" is being installed, prior to the installation of the new steel feeder main.


A map, showing where the new “concrete carrier pipe” is being installed, prior to the installation of the new steel feeder main.

Source: City of Calgary

Stage B of the project, which involved open-cut construction, also began last month on 77 Street and 83 Street N.W., between 33 and 34 Avenue N.W. and the city says all affected roadways have been paved and reopened.


The new steel pipe being used for the feeder main is expected to begin arriving in Calgary within a week and require construction of open trenches along 34 Avenue Northwest, between 79 and 80 Street and 85 to 86 Street to allow for the first sections of new steel pipe to be installed.

“We are digging up the road right down 34 Avenue — so basically we’re going to be excavating approximately from the back of the sidewalk on the north side to the back the sidewalk of the south side,” said Darren Finney, manager of the Bearspaw Feeder Main project.

Story continues below advertisement

The city says that despite the work being done to replace the feeder main, the old pipe could still break again at any time — and before the new feeder main is put into service, there will need to be another shutdown of the system this fall, to allow the different sections of the new pipe to be connected.

“We’re not in the clear yet, but by the end of this year we’re going to have the brand-new pipe built so we we solve this once and for all and we’re never going to be in this situation again,” said Mayor Jeromy Farkas.


Click to play video: 'Calgary drivers trapped, work underway after another water main break '


Calgary drivers trapped, work underway after another water main break 


The city has set up a community resource centre at the Bowness Community Association to help keep residents and businesses affected  construction informed about the project.

Information is also available online on the city’s website, printed notices and information letters are being delivered directly to affected homes and specific questions can be directed to the project team by calling 311 or emailing questions to bsfmproject@calgary.ca.

&copy 2026 Global News, a division of Corus Entertainment Inc.

Consumer,News,Politics,Bearspaw South Feeder Main,Calgary water main breakBearspaw South Feeder Main, Calgary water main break, Consumer, News, Politics#Bearspaw #South #Feeder #Main #replacement #project #schedule #City #Calgary1781564224

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Popular Articles